Boeing IRC Building 88-050

9775 Patriot Blvd
Palmetto Commerce Park
Ladson, SC 29456

1,500 Tons of Structural Steel

Furnish

Years: November, 2010-November, 2011

brph Architects and Engineers

Original Erection Duration: 16 Weeks
Final Erection Duration: 16 Weeks

The Boeing Company
Chicago, Il 60606

boeing-irc-1

Boeing IRC Building 88-50 is a 297,000 square foot manufacturing facility to include 40,000 square feet of mezzanine framing. The facility is located in a high SEISMIC design zone; SteelFab Engineering was able to complete the SEISMIC design that allowed fabrication & erection of the facility with no issues. This project required a fabrication facility that could support an aggressive erection schedule. SteelFab coordinated a sequenced schedule which supported multiple timed deliveries enabling the erection crew to work 6 to 7 days per week. Steel erection was completed in 16 weeks.

Related Projects

Start typing and press Enter to search