Kia Paint Shop

7777 Kia Parkway
West Point, GA 31833

498,500 Square Feet
2921 Tons of Structural Steel

Furnish and Install Structural Steel & Misc. Material

Years: April 2008-September 2008

Albert Kahn Associates, Inc.

Original Erection Duration – 24.5 Weeks
Final Erection Duration – 26 Weeks

TKS Industrial
901 Tower Drive, Suite 250
Troy, Michigan 48098- 2817

kia

Kia Paint Facility had multiple design changes throughout the project and SteelFab was able to keep the project on the original scheduled completion date.