Johns Hopkins Hospital Adult and Children’s Tower Expansions

101-photo-112

1790 Orleans Street
Baltimore, MD 21231

1,500,000 Square Feet
9,775 Tons of Structural Steel

Furnish and Erect

Years: November, 2008-August, 2009

Perkins + Will / Thornton Tomasetti Engineers

Original Erection Duration – 40 Weeks
Final Erection Duration – 40 Weeks

Johns Hopkins Hospital
1790 Orleans Street
Baltimore, MD 21231

The Johns Hopkins Hospital added a Children’s Bed Tower and an Adult Bed Tower to their downtown Baltimore campus. In addition to the two 14 story towers, SteelFab fabricated and erected 3 pedestrian bridges, an AESS canopy, and a 100 ton renovation to the existing parking garage. The project was one of the largest healthcare projects built in the United States in the last 10 years. The project was featured in several construction industry magazines and was on the cover of Modern Steel Construction