Gwinnett Arena

600 Sugarloaf Parkway
Duluth, GA 30097

200,000 Square Feet
3,000 tons of structural steel

Furnish and Erect

Years: April 2001-February 2003

WP Moore

Original Erection Duration – 32 Weeks
Final Erection Duration – 32 Weeks

Gwinnett Civic and Cultural Center
600 Sugarloaf Parkway
Duluth, GA 30097

76-photo-121

The Gwinnett Civil and Cultural Center consisted of an arena for sporting and music events along with a ball room to host conventions. The high roof of the arena was supported by two 240’ long super trusses.